Scheduled outage performance in APSPDCL April-2022 To June-2022
# Sub-Division Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 ATMAKURU 51 13 38 74.51
2 GUDUR 100 9 91 91.00
3 NANDIKOTKUR 73 10 63 86.30
Total 200 8 192 96.00