Scheduled outage performance in APSPDCL July-2022 To September-2022
# Sub-Division Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 KURNOOL 57 1 56 98.25
2 KURNOOL OPERATION 87 5 82 94.25
3 KURNOOL-II 30 0 30 100.00
Total 174 6 168 96.55