Scheduled outage performance in APSPDCL October-2021 To December-2021
# Section Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 AE D1 13 0 13 100.00
2 AE D2 14 1 13 92.86
3 AE D3 10 0 10 100.00
4 AE KOWTHALAM 98 27 71 72.45
5 AE RURALS 97 24 73 75.26
Total 232 52 180 77.59