Scheduled outage performance in APSPDCL April-2022 To June-2022
# Sub-Division Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 PULIVENDULA 48 37 11 22.92
2 PULIVENDULA(RURALS) 14 3 11 78.57
3 VEMPALLI 92 24 68 73.91
Total 289 29 260 89.97