Scheduled outage performance in APSPDCL October-2022 To December-2022
# Section Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 JAMMALAMADUGU 5 0 5 100.00
2 JAMMALAMADUGU RURAL 12 1 11 91.67
3 KONDAPURAM-JML 21 2 19 90.48
4 MUDDANUR 2 0 2 100.00
5 MYLAVARAM-JML 30 6 24 80.00
6 PEDDAMUDIAM 5 0 5 100.00
Total 75 9 66 88.00