Scheduled outage performance in APSPDCL October-2021 To December-2021
# Section Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 KAMALAPURAM 13 5 8 61.54
2 V.N.PALLI 2 0 2 100.00
3 YERRAGUNTLA 11 0 11 100.00
4 YERRAGUNTLA RURAL 6 1 5 83.33
Total 37 0 37 100.00