Scheduled outage performance in APSPDCL October-2021 To December-2021
# Sub-Division Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 JAMMALAMADUGU 34 3 31 91.18
2 PRODDATUR 37 0 37 100.00
3 PRODDATUR RURALS 38 0 38 100.00
4 YERRAGUNTLA 32 6 26 81.25
Total 214 3 211 98.60