Scheduled outage performance in APSPDCL April-2022 To June-2022
# Section Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 ATLOOR 18 0 18 100.00
2 B MATTAM 25 2 23 92.00
3 BADVEL-I 28 0 28 100.00
4 BADVEL-II 28 0 28 100.00
Total 99 2 97 97.98