Scheduled outage performance in APSPDCL Apr-2021 To Jun-2021
# Sub-Division Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 KALYANDURG HQ 24 0 24 100.00
2 KALYANDURG RURALS 25 12 13 52.00
3 RAYADURG 45 4 41 91.11
4 URAVAKONDA 12 0 12 100.00
Total 284 24 260 91.55