Scheduled outage performance in APSPDCL July-2022 To September-2022
# Sub-Division Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 HINDUPUR 24 3 21 87.50
2 HINDUPUR RURALS 14 4 10 71.43
3 MADAKASIRA 33 1 32 96.97
4 PENUKONDA 48 5 43 89.58
Total 79 6 73 92.41