Scheduled outage performance in APSPDCL January-2022 To March-2022
# Sub-Division Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 HINDUPUR 34 8 26 76.47
2 HINDUPUR RURALS 40 18 22 55.00
3 MADAKASIRA 51 3 48 94.12
4 PENUKONDA 73 7 66 90.41
Total 51 12 39 76.47