Scheduled outage performance in APSPDCL October-2021 To December-2021
# Section Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 ATMAKUR 1 0 1 100.00
2 GARLADINNE 8 2 6 75.00
3 KUDERU 10 1 9 90.00
4 RAPTADU 17 0 17 100.00
5 SINGANAMALA 15 9 6 40.00
Total 13 1 12 92.31