Resolution of Billing complaints in APSPDCL where additional information is required Oct-2020 To Dec-2020
# Division Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 CHITTOOR RURALS 20 0.04 10.07 3.35 90.00
2 CHITTOOR TOWN 29 0.2 16.08 2.57 96.55
3 MADANAPALE 26 0.09 15.78 2.47 84.62
4 PILERU 18 0.24 7.82 3.03 88.89
5 PUTTUR 38 0.01 8.17 1.97 97.37
6 TIRUPATI RURALS 36 0.1 19.61 3.27 86.11
7 TIRUPATI TOWN 98 0.01 6.95 1.27 100.00
Total 265 0.01 19.61 2.18 94.34