Resolution of Billing complaints in APSPDCL where additional information is required Oct-2020 To Dec-2020
# Section Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 OPN SUBSTATION-TPT 7 0.06 2.2 0.74 100.00
2 TIRUCHANUR CCO 13 0.31 5.09 1.32 100.00
3 TIRUPATI RURALS II 3 0.06 3.24 1.42 100.00
4 TIRUPATI SOUTH 3 0.25 0.77 0.51 100.00
Total 26 0.06 5.09 1.08 100.00