Replacement of Burnt meters by APSPDCL where cause is attributable to licensee January-2022 To March-2022
# Circle Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 ANANTHAPUR 2 1.01 2.59 1.8 100.00
2 KADAPA 2 0.14 2.78 1.46 100.00
3 NELLORE 2 0.38 1.15 0.76 100.00
4 TIRUPATI 1 1.66 1.66 1.66 100.00
Total 7 0.14 2.78 1.39 100.00