Replacement of Burnt meters by APSPDCL where cause is attributable to consumer April-2022 To June-2022
# Circle Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 ANANTHAPUR 1459 0.02 14.07 2.43 95.75
2 KADAPA 947 0.04 8.98 3.92 98.42
3 KURNOOL 2073 0.01 13.07 2.75 93.54
4 NELLORE 1635 0.08 10.21 3.42 92.17
5 TIRUPATI 1386 0.01 9.78 3.89 96.46
Total 7500 0.01 14.07 3.19 94.83