Replacement of Burnt meters by APSPDCL where cause is attributable to consumer April-2022 To June-2022
# Sub-Division Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 KARVETINAGARAM 21 0.56 6.49 3.73 100.00
2 NAGALAPURAM 60 1.0 8.51 4.37 91.67
3 NAGARI 37 0.38 6.92 3.41 100.00
4 PUTTUR 63 0.27 8.92 3.72 95.24
Total 181 0.27 8.92 3.87 95.58