Replacement of Burnt meters by APSPDCL where cause is attributable to consumer April-2022 To June-2022
# Sub-Division Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 GOOTY 44 0.47 4.41 1.41 100.00
2 GUNTAKAL 56 0.1 13.34 3.39 92.86
3 TADIPATRI 99 0.02 12.25 2.55 90.91
4 TADIPATRI CCO 3 0.93 1.3 1.14 100.00
Total 796 0.02 13.93 2.1 97.24