Release of New Services / Additional Loads where network expansion required -- LT APSPDCL July-2022 To September-2022
# Circle Number of Services Released LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Services Released(%) LT
1 ANANTHAPUR 966 0.01 64.19 18.04 96.69
2 KADAPA 755 0.05 80.73 22.08 79.60
3 KURNOOL 709 0.05 57.59 21.22 87.02
4 NELLORE 988 0.01 39.53 18.49 94.74
5 TIRUPATI 1186 0.0 53.53 18.06 85.67
Total 4604 0.0 80.73 19.58 88.74