Release of New Services / Additional Loads where network expansion required -- LT APSPDCL April-2022 To June-2022
# Sub-Division Number of Services Released LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Services Released(%) LT
1 KARVETINAGARAM 22 5.66 92.95 20.24 95.45
2 NAGALAPURAM 48 1.78 61.97 25.44 58.33
3 NAGARI 9 1.87 24.4 13.59 100.00
4 PUTTUR 39 1.54 74.95 25.66 79.49
Total 118 1.54 92.95 21.23 83.32