Release of New Services / Additional Loads where network expansion required -- LT APSPDCL July-2021 To September-2021
# Sub-Division Number of Services Released LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Services Released(%) LT
1 ALLAGADDA 11 1.12 42.12 22.57 72.73
2 KOILAKUNTLA 15 14.12 67.12 32.19 60.00
3 NANDYAL RURALS 67 0.12 50.12 21.52 89.55
4 NANDYAL TOWN 117 0.12 49.12 20.28 99.15
Total 210 0.12 67.12 24.14 80.36