Release of New Services / Additional Loads where network expansion required -- LT APSPDCL April-2022 To June-2022
# Section Number of Services Released LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Services Released(%) LT
1 BELLARY ROAD 24 14.54 51.84 26.89 87.50
2 CENTRAL SECTION 11 25.54 41.66 27.19 90.91
3 POWER HOUSE 44 6.7 25.87 17.38 100.00
4 SANTHOSH NAGAR 40 12.05 32.7 19.76 97.50
Total 119 6.7 51.84 22.81 93.98