Release of New Services / Additional Loads where network expansion required -- LT APSPDCL July-2021 To September-2021
# Section Number of Services Released LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Services Released(%) LT
1 KAMALAPURAM 1 9.12 9.12 9.12 100.00
2 V.N.PALLI 2 28.12 46.12 37.12 50.00
3 YERRAGUNTLA 1 0.12 0.12 0.12 100.00
4 YERRAGUNTLA RURAL 4 0.12 30.12 13.37 75.00
Total 8 0.12 46.12 14.93 81.25