Release of New Services / Additional Loads from Existing Network in APSPDCL - 33kV July-2022 To September-2022
# Sub-Division Number of Services Released 33kv Min Duration(Days)33kv Max Duration(Days)33kv Average Duration(Days)33kv Services Released(%)33kv
1 NAGALAPURAM OPERATION 3 35.07 98.05 71.75 66.67
Total 3 35.07 98.05 71.75 66.67