# | Sub-Division | Number of Services Released 33kv | Min Duration(Days)33kv | Max Duration(Days)33kv | Average Duration(Days)33kv | Services Released(%)33kv |
---|---|---|---|---|---|---|
1 | ANANTAPUR-II | 1 | 12.67 | 12.67 | 12.67 | 100.00 |
2 | ANANTHAPUR | 2 | 0.83 | 24.75 | 12.79 | 100.00 |
3 | ANANTHAPUR(E) | 2 | 40.96 | 109.96 | 75.46 | 50.00 |
4 | DHARMAVARAM | 1 | 62.96 | 62.96 | 62.96 | 100.00 |
Total | 6 | 0.83 | 109.96 | 42.02 | 83.33 |