Release of New Services / Additional Loads where network expansion required in APSPDCL - 11kV July-2022 To September-2022
# Circle Number of Services Released 11kv Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Services Released(%)11kv
1 ANANTHAPUR 6 9.84 55.92 35.96 100.00
2 KADAPA 9 16.81 67.26 43.27 77.78
3 KURNOOL 6 39.65 70.06 56.51 50.00
4 NELLORE 11 22.02 68.33 37.67 90.91
5 TIRUPATI 17 11.82 70.46 38.67 88.24
Total 49 9.84 70.46 41.14 83.67