Release of New Services / Additional Loads where network expansion required in APSPDCL - 11kV January-2022 To March-2022
# Circle Number of Services Released 11kv Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Services Released(%)11kv
1 ANANTHAPUR 8 4.75 67.88 30.2 87.50
2 KADAPA 5 4.83 71.75 40.22 80.00
3 KURNOOL 8 6.83 80.83 50.32 75.00
4 NELLORE 8 8.82 61.92 30.54 87.50
5 TIRUPATI 12 4.75 76.78 36.48 75.00
Total 41 4.75 80.83 37.25 80.49