Release of New Services / Additional Loads where network expansion required in APSPDCL - 11kV Apr-2021 To Jun-2021
# Circle Number of Services Released 11kv Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Services Released(%)11kv
1 ANANTHAPUR 1 18.0 18.0 18.0 100.00
2 KURNOOL 3 51.0 62.0 57.33 0.00
3 NELLORE 2 26.0 55.0 40.5 50.00
4 TIRUPATI 3 3.0 37.0 20.67 100.00
Total 9 3.0 62.0 37.0 55.56