Release of New Services / Additional Loads where network expansion required in APSPDCL - 11kV Oct-2020 To Dec-2020
# Sub-Division Number of Services Released 11kv Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Services Released(%)11kv
1 RENIGUNTA 1 88.99 88.99 88.99 0.00
2 TIRUPATI OPERATION1 1 93.99 93.99 93.99 0.00
3 TIRUPATI OPERATION2 2 125.99 137.0 131.49 0.00
Total 4 88.99 137.0 111.49 0.00