Release of New Services / Additional Loads where network expansion required in APSPDCL - 11kV January-2022 To March-2022
# Section Number of Services Released 11kv Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Services Released(%)11kv
1 THOTTAMBEDU 2 54.75 56.83 55.79 100.00