Release of New Services / Additional Loads where network expansion required in APSPDCL - 11kV January-2022 To March-2022
# Sub-Division Number of Services Released 11kv Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Services Released(%)11kv
1 SRIKALAHASTI 2 54.75 56.83 55.79 100.00
Total 3 11.65 58.92 28.16 100.00