Release of New Services / Additional Loads where network expansion required in APSPDCL - 11kV October-2022 To December-2022
# Sub-Division Number of Services Released 11kv Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Services Released(%)11kv
1 KARVETINAGAR CCO 2 43.27 56.98 50.12 100.00
2 NAGALAPURAM OPERATION 2 36.71 61.29 49.0 50.00
3 PUTTUR OPERATION 1 37.16 37.16 37.16 100.00
Total 5 36.71 61.29 47.08 80.00