Release of New Services / Additional Loads where network expansion required in APSPDCL - 11kV October-2021 To December-2021
# Section Number of Services Released 11kv Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Services Released(%)11kv
1 KONGAREDDI PALLI 1 25.66 25.66 25.66 100.00
2 MITTOOR NORTH 3 7.66 10.66 9.03 100.00
Total 4 7.66 25.66 13.19 100.00