Release of New Services / Additional Loads where network expansion required in APSPDCL - 11kV October-2022 To December-2022
# Sub-Division Number of Services Released 11kv Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Services Released(%)11kv
1 CHITTOOR RURAL-III 2 30.92 32.85 31.88 100.00