Release of New Services / Additional Loads where network expansion required in APSPDCL - 11kV October-2022 To December-2022
# Division Number of Services Released 11kv Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Services Released(%)11kv
1 GUDUR 1 39.65 39.65 39.65 100.00
2 KAVALI 1 36.58 36.58 36.58 100.00
3 NAIDUPETA 1 34.77 34.77 34.77 100.00
4 NELLORE RURALS 2 27.12 68.03 47.57 50.00
5 NELLORE TOWN 3 49.78 53.75 51.83 100.00
Total 8 27.12 68.03 45.2 87.50