Release of New Services / Additional Loads where network expansion required in APSPDCL - 11kV Apr-2021 To Jun-2021
# Division Number of Services Released 11kv Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Services Released(%)11kv
1 KAVALI 1 26.0 26.0 26.0 100.00
2 NELLORE RURALS 1 55.0 55.0 55.0 0.00
Total 2 26.0 55.0 40.5 50.00