Release of New Services / Additional Loads where network expansion required in APSPDCL - 11kV April-2022 To June-2022
# Sub-Division Number of Services Released 11kv Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Services Released(%)11kv
1 NELLORE TOWN-I 1 42.49 42.49 42.49 100.00
2 NELLORE TOWN-II 2 13.83 19.7 16.77 100.00
Total 3 13.83 42.49 25.34 100.00