Release of New Services / Additional Loads where network expansion required in APSPDCL - 11kV October-2022 To December-2022
# Sub-Division Number of Services Released 11kv Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Services Released(%)11kv
1 INDUKURPETA C AND O 1 68.03 68.03 68.03 0.00
2 NELLORE RURALS 1 27.12 27.12 27.12 100.00
Total 2 27.12 68.03 47.57 50.00