Release of New Services / Additional Loads where network expansion required in APSPDCL - 11kV July-2021 To September-2021
# Sub-Division Number of Services Released 11kv Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Services Released(%)11kv
1 INDUKURPET 1 59.12 59.12 59.12 100.00
2 NELLORE RURA 1 17.12 17.12 17.12 100.00
3 PODALAKUR 1 27.12 27.12 27.12 100.00
Total 3 17.12 59.12 34.45 100.00