Release of New Services / Additional Loads where network expansion required in APSPDCL - 11kV Apr-2020 To Sep-2020
# Sub-Division Number of Services Released 11kv Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Services Released(%)11kv
1 NELLORE RURALS 2 18.0 230.0 124.0 50.00
2 PODALAKUR C AND O 1 89.0 89.0 89.0 0.00
Total 3 18.0 230.0 112.33 33.33