Release of New Services / Additional Loads where network expansion required in APSPDCL - 11kV July-2021 To September-2021
# Section Number of Services Released 11kv Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Services Released(%)11kv
1 MANUBOLU 1 44.12 44.12 44.12 100.00
2 SYDAPURAM 1 58.12 58.12 58.12 100.00
Total 2 44.12 58.12 51.12 100.00