Release of New Services / Additional Loads where network expansion required in APSPDCL - 11kV July-2022 To September-2022
# Division Number of Services Released 11kv Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Services Released(%)11kv
1 ADONI 1 52.07 52.07 52.07 100.00
2 KURNOOL 3 47.02 70.06 60.78 33.33
3 NANDYAL 2 39.65 64.98 52.32 50.00
Total 6 39.65 70.06 56.51 50.00