Release of New Services / Additional Loads where network expansion required in APSPDCL - 11kV January-2022 To March-2022
# Division Number of Services Released 11kv Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Services Released(%)11kv
1 ADONI 2 57.87 58.78 58.32 100.00
2 KURNOOL 3 6.83 80.83 49.77 33.33
3 NANDYAL 3 33.82 58.87 45.53 100.00
Total 8 6.83 80.83 50.32 75.00