Release of New Services / Additional Loads where network expansion required in APSPDCL - 11kV July-2021 To September-2021
# Sub-Division Number of Services Released 11kv Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Services Released(%)11kv
1 KOILAKUNTLA 2 37.12 68.12 52.62 50.00
2 NANDYAL RURALS 1 55.12 55.12 55.12 100.00
Total 1 22.12 22.12 22.12 100.00