Release of New Services / Additional Loads where network expansion required in APSPDCL - 11kV January-2022 To March-2022
# Section Number of Services Released 11kv Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Services Released(%)11kv
1 NANDYAL TOWN 1 2 33.82 58.87 46.34 100.00
2 NANDYAL TOWN 2 1 43.9 43.9 43.9 100.00
Total 3 33.82 58.87 45.53 100.00