Release of New Services / Additional Loads where network expansion required in APSPDCL - 11kV April-2022 To June-2022
# Section Number of Services Released 11kv Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Services Released(%)11kv
1 NANDYAL TOWN 3 1 43.6 43.6 43.6 100.00
Total 1 43.6 43.6 43.6 100.00