Release of New Services / Additional Loads where network expansion required in APSPDCL - 11kV July-2022 To September-2022
# Sub-Division Number of Services Released 11kv Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Services Released(%)11kv
1 KURNOOL OPERATION 1 47.02 47.02 47.02 100.00
2 KURNOOL-II 2 65.28 70.06 67.67 0.00
Total 3 47.02 70.06 60.78 33.33