Release of New Services / Additional Loads where network expansion required in APSPDCL - 11kV Apr-2021 To Jun-2021
# Sub-Division Number of Services Released 11kv Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Services Released(%)11kv
1 KURNOOL OPERATION 1 59.0 59.0 59.0 0.00
Total 1 59.0 59.0 59.0 0.00