Release of New Services / Additional Loads where network expansion required in APSPDCL - 11kV July-2021 To September-2021
# Sub-Division Number of Services Released 11kv Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Services Released(%)11kv
1 BADVEL 1 13.12 13.12 13.12 100.00
2 PORUMAMILLA 1 62.12 62.12 62.12 0.00
Total 1 8.12 8.12 8.12 100.00