Release of New Services / Additional Loads where network expansion required in APSPDCL - 11kV July-2022 To September-2022
# Division Number of Services Released 11kv Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Services Released(%)11kv
1 ANANTHAPUR 2 17.68 53.05 35.37 100.00
2 HINDUPUR 3 9.84 55.92 39.57 100.00
3 KADIRI 1 26.32 26.32 26.32 100.00
Total 6 9.84 55.92 35.96 100.00